Eastern Washington’s Wildfire Rebuild: What Spokane-Area Homeowners and Contractors Need to Know

Spokane is now facing the largest rebuilding effort in Washington’s history, and while it sits outside NWCN’s usual I-5 corridor coverage, the regulatory playbook unfolding there — expedited permitting, code-vesting deadlines, and a maze of overlapping jurisdictions — is worth understanding for any contractor who might pick up work in eastern Washington, and worth watching as a preview of how the state responds to major disasters generally.

The scale of the damage

A wind-driven firestorm swept into Spokane and the surrounding area on August 1, made up of three fires — the Old Trails Fire north of Airway Heights, the Autumn Lane Fire near Nine Mile Falls, and the Fairview Fire near Mead — now managed together as the Spokane Complex Fires. Sustained winds gusting to 44 mph, 86-degree heat, and humidity as low as 20% drove the fire through residential neighborhoods including Indian Trail, Five Mile Prairie, and Balboa, destroying homes block by block.

Governor Bob Ferguson’s office now puts the toll at more than 900 homes, businesses, and buildings destroyed, making it the most destructive wildfire in state history. Roughly 65,000 people were placed under evacuation orders at the peak. Spokane County received a federal Presidential Disaster Declaration, and FEMA and SBA disaster-assistance applications are open for residents and businesses. As of mid-August, all evacuation orders in Spokane County have been lifted, though officials say crews remain in some neighborhoods to finish assessing properties.

The state is actively trying to speed up rebuilding

Governor Ferguson issued an emergency proclamation suspending select state laws to help victims recover faster — including waiving license renewal requirements for healthcare workers and suspending standard business filing deadlines and late fees. More significant for the construction industry: officials say part of that declaration directs the state Building Code Council to review permitting processes and building codes with the specific goal of helping people rebuild “as fast and safe as possible.”

That’s a meaningful signal. When a state building code authority is asked to look at streamlining permitting in direct response to a disaster, the resulting changes can ripple beyond the immediate fire zone — worth watching for any precedent that could eventually touch permitting reform conversations in Oregon and southwest Washington too.

Locally, the Spokane Home Builders Association has already cut its demolition permit fee to $33.62 for wildfire-affected properties, and both Spokane County and the City of Spokane have stood up dedicated “Rebuilding” information hubs walking homeowners through debris removal, permitting, and construction sequencing step by step.

A code-vesting deadline that matters right now

Here’s the detail with the most direct relevance to builders: Washington’s 2024 building code editions are targeted for adoption on August 28, 2026, with an effective date of May 3, 2027. Under state law, a project “vests” — meaning it locks in the code edition in effect — when a complete permit application is filed, not when the permit is actually issued.

That timing matters because Washington’s Wildland-Urban Interface (WUI) construction requirements are currently on hold, pending wildfire hazard maps the state hasn’t finished drafting. For homeowners and contractors racing to rebuild, filing a genuinely complete application soon could mean building under today’s code rather than a future WUI-influenced standard — but “complete” is doing a lot of work in that sentence, and permitting offices should be asked in writing exactly what qualifies.

Permitting is not one office — it’s eight

One of the more practical headaches for any contractor working across the burn area: “Spokane” isn’t a single permitting authority. Unincorporated Spokane County, the City of Spokane, Spokane Valley, Airway Heights, Medical Lake, Deer Park, Cheney, and Liberty Lake each run their own permitting departments, with their own local amendments, fees, and timelines — and each will land on its own answer for how strictly to apply wildfire-related construction requirements. A parcel’s exact jurisdiction determines which building department has authority over it, and that has to be confirmed before anything else in the process moves forward.

Debris removal has its own regulatory sequence

Before rebuilding can start, cleanup has to clear several checkpoints:

  • Asbestos survey and Notice of Intent — homes built before the 1990s typically require an AHERA-certified inspector to survey the site before any demolition or debris removal, with a Notice of Intent filed with the Spokane Regional Clean Air Agency. This step applies even to small structures.
  • Erosion control permits — required if debris removal or grading will disturb soil, particularly on sloped lots or near waterways.
  • Temporary power permits — needed before utilities will reconnect service to a site for construction equipment, lighting, or trailers.
  • Right-of-way/access permits — required if debris bins, equipment, or trucks will be staged on or block a public street.

As of early August, Spokane Regional Solid Waste was still asking property owners to hold off on independent cleanup while the county coordinated a broader debris removal process — a coordination step that, in past wildfire recoveries elsewhere, has significantly shaped how quickly rebuilding actually gets underway.

The building industry is mobilizing

The National Association of Home Builders is coordinating with state and local home builder associations across eastern Washington to support members and communities affected by the fires. The Spokane Home Builders Association’s Frame Your Future Foundation is running a Spokane Wildfire Disaster Relief Fund, a 501(c)(3) accepting tax-deductible contributions to support the hardest-hit communities.

Why this matters beyond Spokane

Eastern Washington’s rebuild is a different market than the I-5 corridor, but the regulatory questions playing out there — how fast a state Building Code Council can move to streamline disaster permitting, how code-vesting deadlines interact with pending hazard-map rules, and how multiple overlapping jurisdictions coordinate (or don’t) during a crisis — are exactly the kind of translation work NWCN does for its readers on OR/WA legislative and permitting stories generally. We will follow-up once the state Building Code Council’s review concludes, to see what precedent it sets.

Sources:


Koleena

Koleena has been a business owner for nearly 30 years. A serial entrepreneur, she has owned an event business coordinating local trade shows, a Christmas store and has been an approved provider for the Oregon CCB pre-license training class for new contractors since 2007. Prior to that, she worked in construction administration in several capacities. Dabbling in various other interests, her favorite hobby is gardening. She loves watching her plants grow and her students grow to their full-potential as business owners.